Progress Timeline

OAS Construction - Easy Imports. 

Professional Visual Documentation for Construction & Property Projects

Project Objective

The objective of this roofing project was to restore and improve the integrity of the existing roof system through targeted replacement and comprehensive sealing. OAS Roofing completed the necessary work to address vulnerable and deteriorated areas, helping create a more secure and weather-resistant roofing system.

Project Scope

As of August 8, the project reached its final stage, with the planned roof replacement and sealing work substantially completed. Final activities focused on remaining roof areas, reinforcing critical sections, and completing sealing measures to help prevent future water intrusion.

Safety Observation Snapshot

  • PPE Compliance: Required PPE was visibly utilized by personnel observed during the site visit.

  • Safety Observations: Work areas appeared organized, with roof-access areas and active work zones clearly maintained. Fall-protection equipment was observed during elevated roofing activities.

  • Corrective Actions: No corrective actions were observed or reported during this documentation period.

  • Site Safety Photos: Photographic documentation of PPE use, roof access, fall protection, and general work-site conditions included in this report.

Drone Videos - Monthly Visual Timeline

Project Timeline Overview June 15

Timeline video shows that the South West fact of the project was not started at the time of our visit, but the whole east part of the project has been started and the South wing was being scraped so the staff can start working on it.

Key Construction Changes Plastic protection on the room was installed and sealed.

Key Construction Changes Plastic protection on the room was installed and sealed.

Project Timeline Overview June 30

Timeline video shows that the South West fact of the project was not started at the time of our visit, but the whole east part of the project has been started and the South wing was being scraped so the staff can start working on it.

 

Key Construction Changes Plastic protection on the room was installed and sealed.

Key Construction Changes Plastic protection on the room was installed and sealed.

Project Timeline Overview July 15

Timeline video shows that the South West fact of the project was not started at the time of our visit, but the whole east part of the project has been started and the South wing was being scraped so the staff can start working on it.

 

Key Construction Changes Plastic protection on the room was installed and sealed.

Key Construction Changes Plastic protection on the room was installed and sealed.

Project Timeline Overview July 30

Timeline video shows that the South West fact of the project was not started at the time of our visit, but the whole east part of the project has been started and the South wing was being scraped so the staff can start working on it.

 

Key Construction Changes Plastic protection on the room was installed and sealed.

Key Construction Changes Plastic protection on the room was installed and sealed.

Ground Videos - Monthly Visual Timeline

Project Timeline Overview June 15

Timeline video shows that the South West fact of the project was not started at the time of our visit, but the whole east part of the project has been started and the South wing was being scraped so the staff can start working on it.

Key Construction Changes Plastic protection on the room was installed and sealed.

Key Construction Changes Plastic protection on the room was installed and sealed.

Project Timeline Overview June 30

Timeline video shows that the South West fact of the project was not started at the time of our visit, but the whole east part of the project has been started and the South wing was being scraped so the staff can start working on it.

 

Key Construction Changes Plastic protection on the room was installed and sealed.

Key Construction Changes Plastic protection on the room was installed and sealed.

Project Timeline Overview July 15

Timeline video shows that the South West fact of the project was not started at the time of our visit, but the whole east part of the project has been started and the South wing was being scraped so the staff can start working on it.

 

Key Construction Changes Plastic protection on the room was installed and sealed.

Key Construction Changes Plastic protection on the room was installed and sealed.

Project Timeline Overview July 30

Timeline video shows that the South West fact of the project was not started at the time of our visit, but the whole east part of the project has been started and the South wing was being scraped so the staff can start working on it.

 

Key Construction Changes Plastic protection on the room was installed and sealed.

Key Construction Changes Plastic protection on the room was installed and sealed.

Ground and Drone Photographies - Monthly Visual Timeline

Project Timeline Overview June 15

Timeline video shows that the South West fact of the project was not started at the time of our visit, but the whole east part of the project has been started and the South wing was being scraped so the staff can start working on it.

Key Construction Changes Plastic protection on the room was installed and sealed.

Key Construction Changes Plastic protection on the room was installed and sealed.

Project Timeline Overview June 30

Timeline video shows that the South West fact of the project was not started at the time of our visit, but the whole east part of the project has been started and the South wing was being scraped so the staff can start working on it.

Key Construction Changes Plastic protection on the room was installed and sealed.

Key Construction Changes Plastic protection on the room was installed and sealed.

Project Timeline Overview July 15

Timeline video shows that the South West fact of the project was not started at the time of our visit, but the whole east part of the project has been started and the South wing was being scraped so the staff can start working on it.

Key Construction Changes Plastic protection on the room was installed and sealed.

Key Construction Changes Plastic protection on the room was installed and sealed.

Project Timeline Overview July 30

Timeline video shows that the South West fact of the project was not started at the time of our visit, but the whole east part of the project has been started and the South wing was being scraped so the staff can start working on it.

 

Key Construction Changes Plastic protection on the room was installed and sealed.

Key Construction Changes Plastic protection on the room was installed and sealed.

Virtual Tour - Monthly Visual Timeline

contact us

Drone Productions 

juanp@droneproductions.co

🇺🇸 +1     305 394-8701

🇨🇴 +57  304 565-1918

🇺🇸   1111 SW 1st Ave. 

        Miami, FL. 33130

🇨🇴   Calle 9 Sur #79C

        Medellin, Colombia

Download Contact Card

© 2026 by Drone Productions

  • Whatsapp
  • Instagram
  • LinkedIn
  • Facebook
  • TikTok
bottom of page